# The Sheringham Shoal and Dudgeon Extensions Offshore Wind Farm Order 2024, Paragraph 5

Extent: E+W

Offshore Platform dimensions
The dimensions of any offshore substation platform (excluding towers, masts and cranes) must not exceed—
(a) 70 metres in length;
(b) 40 metres in width; or
(c) 50 metres in height above HAT.

---