# The Sheringham Shoal and Dudgeon Extensions Offshore Wind Farm Order 2024, Paragraph 1: Applications made under requirements

Extent: E+W

Where an application has been made to the relevant authority (“the approving authority”) for any agreement or approval required pursuant to a requirement included in this Order, the approving authority must give notice to the undertaker of their decision, including the reasons, on the application, within a period of 56 days beginning with—
(a) the day immediately following that on which the application is received by the approving authority;
(b) where further information is requested under paragraph 2, the day immediately following that on which the further information has been supplied by the undertaker; or
(c) such longer period as may be agreed by the undertaker and the approving authority.

---
Source: https://www.legislation.gov.uk/uksi/2024/564/schedule/2/part/2/paragraph/1 (the official version)
Page: https://openlegislation.uk/sheringham-shoal-and-dudgeon-extensions-offshore-wind-farm-order-2024/schedule-2/part-2/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.