# The Sheringham Shoal and Dudgeon Extensions Offshore Wind Farm Order 2024, Paragraph 3: Provision of information by Consultees

Extent: E+W

(1) Any consultee who receives a consultation under sub-paragraph 2(3) must respond to that request within 28 days from receipt unless either sub-paragraph ‎(2) of this paragraph applies or a longer period is agreed with both the undertaker and the approving authority.
(2) Where any consultee requests further information in accordance with the timescales set out in sub-paragraph 2(3) then they must respond to the consultation within 14 days from the receipt of the further information requested unless a longer period is agreed with both the undertaker and the approving authority.

---
Source: https://www.legislation.gov.uk/uksi/2024/564/schedule/2/part/2/paragraph/3 (the official version)
Page: https://openlegislation.uk/sheringham-shoal-and-dudgeon-extensions-offshore-wind-farm-order-2024/schedule-2/part-2/paragraph-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.