# The Silvertown Tunnel Order 2018, Paragraph 14: Further information regarding application


(1) The MMO may request in writing such further information from the licence holder as is necessary to enable the MMO to consider the application.
(2) If the MMO does not make a request under sub-paragraph (1) within 20 business days of the day immediately following that on which the application is received by the MMO, it is deemed to have sufficient information to consider the application and is not entitled to request further information after this date without the prior agreement of the licence holder.

---