# The Single Source Contract (Amendment) Regulations 2024, Regulation 5: Amendment of regulation 4 (meaning of “contract completion date”)


In regulation 4—
(a) in the heading, at the end insert “and “component completion date””;
(b) in paragraph (1)—
(i) omit sub-paragraph (a) (and the “or” at the end);
(ii) in sub-paragraph (b), omit “if no such date is described in the contract,”;
(iii) in sub-paragraph (c), for “(1)(a) or (b) (as the case may be)” substitute “(1)(b)”;
(c) after paragraph (1) insert—
“(1A) The “component completion date”, in relation to a component of a contract, means—
(a) the date on which the contractor completes all obligations under that component which entitle it to final payment in respect of that component;
(b) if that component is terminated, but any other part of the contract is not terminated, before the date described in sub-paragraph (a), the date on which the component is terminated.”;
(d) in the opening words of paragraph (2)—
(i) after “(1)(b)” insert “and (1A)(a)”;
(ii) after “contract” insert “or in respect of a component”.

---
Source: https://www.legislation.gov.uk/uksi/2024/420/regulation/5 (the official version)
Page: https://openlegislation.uk/single-source-contract-amendment-regulations-2024/regulation-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.