# The Sizewell C (Nuclear Generating Station) Order 2022, Article 12: Defence to proceedings in respect of statutory nuisance


(1) Where proceedings are brought under section 82(1) of the Environmental Protection Act 1990 (Summary proceedings by person aggrieved by statutory nuisance) in relation to a nuisance falling within sub-paragraphs (d), (fb), (g) or (ga) of section 79(1) of that Act (statutory nuisances and inspections thereof) no order may be made, and no fine may be imposed, under section 82(2) of that Act if the defendant shows that the nuisance—
(a) relates to premises used by the undertaker for the purposes of or in connection with the construction, maintenance or operation of the authorised development and that the nuisance is attributable to the carrying out or use of the authorised development in accordance with—
(i) a notice served under section 60 (control of noise on construction site);
(ii) a consent given under section 61 (prior consent for work on construction site); or
(iii) the controls and measures relating to noise, vibration, dust or lighting as described in the Construction Method Statement, Code of Construction Practice, Lighting Management Plan, Main Development Site Design and Access Statement, Associated Development Design Principles and Outline Landscape and Ecology Management Plan or in accordance with noise and lighting levels set out in an environmental permit relating to the construction, maintenance or operation of the authorised development; or
(b) is a consequence of the construction, maintenance or operation of the authorised development and that it cannot, to the reasonable satisfaction of East Suffolk Council reasonably be avoided.
(2) Sections 61(9) of the Control of Pollution Act 1974 (consent for work on construction sites) as it relates to proceedings under section 82 of the Environmental Protection Act 1990 (Summary proceedings by persons aggrieved by statutory nuisance) does not apply where the consent relates to the use of premises by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised development.
(3) In this article “premises” has the same meaning as in section 79 of the Environmental Protection Act 1990.

---
Source: https://www.legislation.gov.uk/uksi/2022/853/article/12 (the official version)