# The Sizewell C (Nuclear Generating Station) Order 2022, Article 21: Access to works


(1) The undertaker may, for the purposes of the authorised development—
(a) form and lay out means of access, or improve existing means of access identified on the Rights of Way Plans; and
(b) with the approval of the street authority after consultation with the highway authority (such approval not to be unreasonably withheld), form and lay out means of access or improve existing means of access at such other locations within the Order limits as the undertaker reasonably requires.
(2) If a street authority that receives an application for approval under paragraph (1)(b) fails to notify the undertaker of its decision within 56 days of receiving the application, that authority will be deemed to have granted approval.

---
Source: https://www.legislation.gov.uk/uksi/2022/853/article/21 (the official version)
Page: https://openlegislation.uk/sizewell-c-nuclear-generating-station-order-2022/article-21
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.