# The Sizewell C (Nuclear Generating Station) Order 2022, Article 74: Duration of the powers in Part 6


(1) Within 28 days following completion of all works for the removal of the temporary marine bulk import facility in accordance with requirement 29, the undertaker must—
(a) appoint, by resolution, a date on which this Part 6 (Harbour Powers) will cease to have effect, which shall be not more than 28 days after the resolution;
(b) publish a notice containing a copy of the resolution proposed to be passed by the undertaker appointing that date in—
(i) Lloyd’s List newspaper or some other newspaper specialising in shipping news;
(ii) a local newspaper circulating in the district of East Suffolk Council; and
(iii) on a website managed by the undertaker.
(2) Except as provided in article 75 (saving for termination of Part 6) this Part 6 will cease to have effect on the date specified in the resolution.

---
Source: https://www.legislation.gov.uk/uksi/2022/853/article/74 (the official version)