Paragraph 105 Sizewell C proposed intake infrastructure

Original text. Later amendments are not shown.

(1)

Save for urgent reasons of vessel safety and subject to sub-paragraph (2), the undertaker shall not carry out any of the authorised development (including the placement temporary or otherwise of anchors or moorings) within the area labelled “Overlap of Sizewell C Order limits with East Anglia ONE North Order limits” and hatched purple on the EA1N Order Limits Interaction – Offshore Plan (Drawing No. SZC-SZ0100-XX-000-DRW-100288) without having first submitted to and secured approval from EA1N details of the proposed method of working within these areas (such approval not to be unreasonably withheld or delayed) and thereafter the undertaker shall implement the authorised project in full accordance with such approved details.

(2)

Nothing in this paragraph shall prevent the passage of vessels within the area specified in sub-paragraph (1) prior to the construction of any works within that location by EA1N at any time.