Save for differences or disputes arising under paragraph 48(2), 48(4) 49(1), 50 and 51 any difference or dispute arising between the undertaker and National Grid under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and National Grid, be determined by arbitration in accordance with article 84 (arbitration).

---