# The Sizewell C (Nuclear Generating Station) Order 2022, Paragraph 66


If for any reason or in consequence of the construction of any of the works referred to in paragraphs 60 to 62 any damage is caused to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of ESW, or there is any interruption in any service provided, or in the supply of any goods, by ESW, the undertaker must—
(a) bear and pay the cost reasonably incurred by ESW in making good any damage or restoring the supply; and
(b) make reasonable compensation to ESW for any other expenses, loss, damages, penalty or costs incurred by ESW, by reason or in consequence of any such damage or interruption.

---
Source: https://www.legislation.gov.uk/uksi/2022/853/schedule/19/paragraph/66 (the official version)
Page: https://openlegislation.uk/sizewell-c-nuclear-generating-station-order-2022/schedule-19/paragraph-66
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.