# The Sizewell C (Nuclear Generating Station) Order 2022, Paragraph 10: Pre-construction


Local mariners, fishermen’s organisations and the UK Hydrographic Office must be notified of any licensed activity or phase of licensed activity through a local Notice to Mariners. A Notice to Mariners must be issued at least 5 days before the commencement of each licensed activity or phase of licensed activity. The MMO and MCA must be sent a copy of the notification within 24 hours of issue. The Notice to Mariners must include—
(a) the start and end dates for the works;
(b) a summary of the works to be undertaken;
(c) the location of the works area, including coordinates in accordance with WGS84; and
(d) any markings of the works area that will be put in place.

---
Source: https://www.legislation.gov.uk/uksi/2022/853/schedule/21/paragraph/10 (the official version)
Page: https://openlegislation.uk/sizewell-c-nuclear-generating-station-order-2022/schedule-21/paragraph-10
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.