# The Sizewell C (Nuclear Generating Station) Order 2022, Paragraph 14: Pre-construction


(1) No licenced activity may commence until a CPMMP (marine) has been submitted to and approved by the MMO in writing in consultation with the Environment Agency. The CPMMP (marine) must be in general accordance with the Draft Coastal Processes Monitoring and Mitigation Plan and must include but is not limited to—
(a) details of the area to be monitored;
(b) the methods for monitoring;
(c) the duration of monitoring;
(d) the trigger points for mitigation;
(e) a description of proposed mitigation;
(f) examples of mitigation measures which could be implemented and which would be effective to mitigate particular results of the monitoring and how the appropriateness of each measure will be considered;
(g) details concerning its proposed review; and
(h) details concerning the appropriate timing for a monitoring and mitigation cessation report to be prepared.
(2) The CPMMP (marine) must be implemented as approved by the MMO.
(3) Monitoring reports, as defined within the CPMMP (marine), must be submitted to the MMO for approval in writing.
(4) Unless a shorter period is agreed with the MMO in writing, the undertaker must use reasonable endeavours to submit the CPMMP (marine) to the MMO at least 6 months prior to the proposed commencement of licenced activities.

---
Source: https://www.legislation.gov.uk/uksi/2022/853/schedule/21/paragraph/14 (the official version)