Paragraph 37 Soft Coastal Defence Feature (SCDF)

Original text. Later amendments are not shown.

(1)

The construction of Work No. 1A(m) must not commence until the following activity details have been submitted to and approved by the MMO in writing in consultation with the Environment Agency. The details must include, but are not limited to—

(a)

the start and end dates for the construction;

(b)

a detailed construction method statement;

(c)

the source, type and grain size of the material to be deposited;

(d)

a description of any proposed mitigation;

(e)

the type and number of vehicles to be used; and

(f)

links to the CPMMP (marine).

(2)

The construction of Work No. 1A(m) must be carried out in accordance with the activity details approved by the MMO.

(3)

Unless a shorter period is agreed with the MMO in writing, the undertaker must use reasonable endeavours to submit the activity details to the MMO at least 6 months prior to the proposed commencement of Work No. 1(A)(m).