# The Sizewell C (Nuclear Generating Station) Order 2022, Paragraph 41: Cooling Water Intake and Outfall Heads, Shafts and Tunnels


(1) The construction of Work Nos. 2A to 2J must not commence until the following activity details for that Work No. have been submitted to and approved by the MMO in writing. The activity details must include, but are not limited to—
(a) the location and design (size and shape) of the cooling water intake and outfall heads;
(b) the alignment (horizontal and vertical) of the cooling water intake and outfall tunnels;
(c) a description of any proposed mitigation;
(d) the location and design of the FRR which must be in accordance with the Environment Agency reports referenced in the Environmental Statement (Volume 2, Chapter 2, Section 2.4(d)) unless otherwise agreed in writing by the MMO; and
(e) any lessons learned from the performance of the FRR at Hinkley Point C if Hinkley Point C is operational.
(2) Work Nos. 2A to 2J must be constructed in accordance with the activity details approved by the MMO.
(3) Unless a shorter period is agreed with the MMO in writing, the undertaker must use reasonable endeavours to submit the activity details at least 6 months prior to the proposed commencement of the relevant Work No.

---
Source: https://www.legislation.gov.uk/uksi/2022/853/schedule/21/paragraph/41 (the official version)
Page: https://openlegislation.uk/sizewell-c-nuclear-generating-station-order-2022/schedule-21/paragraph-41
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.