# The Sizewell C (Nuclear Generating Station) Order 2022, Paragraph 7: Pre-construction


(1) No licensed activity must commence until a detailed and up-to-date programme of works has been submitted to and approved by the MMO in writing. The programme of works must include—
(a) a planned timetable for each activity as outlined in paragraphs 4 and 5 of Part 2 of this licence;
(b) timings for mobilisation of construction plant and for delivery of materials by sea;
(c) a plan for notifying the MMO of the commencement and cessation of activities and phases of activities; and
(d) a plan for notifying the MMO of changes to the programme.
(2) An updated programme of works must be submitted to the MMO in writing every 6 months from the date of approval unless otherwise agreed with the MMO.

---
Source: https://www.legislation.gov.uk/uksi/2022/853/schedule/21/paragraph/7 (the official version)
Page: https://openlegislation.uk/sizewell-c-nuclear-generating-station-order-2022/schedule-21/paragraph-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.