(1) Sizewell B relocated facilities permission 2 condition(2) Order requirement
2, 516 (Main development site: Approved buildings, structures and plant)
18, 19Requirement 6 (Emergency Planning)
15, 22, 235 (Project-wide: Surface and foul water drainage)
20, 213 (Project wide: Archaeology)