Article 4 Authorisation of the operation of the extended generating station
(1)
Subject to the provisions of this Order and the requirements in Schedule 2 the undertaker is authorised to operate the extended generating station.
(2)
Paragraph (1) does not relieve the undertaker of any requirement to obtain any permit or licence under any other legislation that may be required from time to time to authorise the operation of the extended generating station.