# The Slough Multifuel Extension Order 2023, Article 8: Planning permission


(1) If planning permission is issued pursuant to the 1990 Act for development any part of which is within the Order limits following the publication of this Order that is—
(a) not itself a nationally significant infrastructure project under the 2008 Act or part of such a project; and
(b) required to complete or enable the construction, use or operation of any part of the development authorised by this Order or of the extended generating station,
then the carrying out, use, operation or decommissioning of such development pursuant to the terms of the planning permission is not to constitute a breach of the terms of this Order.
(2) Anything done by the undertaker in accordance with this Order does not constitute a breach of any planning permission issued pursuant to the 1990 Act.

---
Source: https://www.legislation.gov.uk/uksi/2023/1278/article/8 (the official version)
Page: https://openlegislation.uk/slough-multifuel-extension-order-2023/article-8
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.