Paragraph 1 Applications made under requirements

Original text. Later amendments are not shown.

Where an application has been made to the relevant planning authority for any consent, agreement or approval required pursuant to a requirement included in this Order, the relevant planning authority must give notice to the undertaker of their decision, including the reasons, on the application, within a period—

(a)

of 8 weeks beginning with the day immediately following that on which the application is received by the relevant planning authority; or

(b)

such longer period as may be agreed by the undertaker and the relevant planning authority.