Paragraph 1 Applications made under requirements
Where an application has been made to the relevant planning authority for any consent, agreement or approval required pursuant to a requirement included in this Order, the relevant planning authority must give notice to the undertaker of their decision, including the reasons, on the application, within a period—
(a)
of 8 weeks beginning with the day immediately following that on which the application is received by the relevant planning authority; or
(b)
such longer period as may be agreed by the undertaker and the relevant planning authority.