In so far as the specified works or the acquisition or use of railway property are or may be subject to railway operational procedures, Railtrack and South West Trains shall—
(a) co-operate with the undertaker with a view to avoiding undue delay and securing conformity as between any plans approved by the engineer and requirements emanating from those procedures; and
(b) use their reasonable endeavours to avoid any conflict arising between the application of those procedures and the proper implementation of the rapid transit system pursuant to the Order.

---