# The South Hook Combined Heat and Power Plant Order 2014, Article 16: Arbitration

Extent: E+W+S

(1) Any difference under any provision of this Order, unless otherwise provided for, must be referred to and finally settled under the rules of arbitration of the International Chamber of Commerce by arbitrators appointed in accordance with those rules of arbitration.
(2) The arbitration must be held in Cardiff (unless otherwise agreed by the parties to the proceedings) and the arbitration proceedings must be conducted, and the award rendered, in the English language.
(3) Where reasonably requested by any party to the proceedings, simultaneous translation of the proceedings will be provided in Welsh and the award translated into the Welsh language.
(4) The resulting arbitral award shall be final and binding without right of appeal, and judgment upon such award may be entered in any court having jurisdiction thereof.

---
Source: https://www.legislation.gov.uk/uksi/2014/2846/article/16 (the official version)