# The South Hook Combined Heat and Power Plant Order 2014, Paragraph 12: Code of Construction Practice

Extent: E+W+S

(1) No authorised development shall commence until a Code of Construction Practice (“CCP”) has been submitted to and approved by the relevant planning authorities. The CCP must reflect the proposals set out in the draft CCP.
(2) All construction works must be undertaken in accordance with the approved CCP, or with such changes to that document as agreed by the relevant planning authorities.

---
Source: https://www.legislation.gov.uk/uksi/2014/2846/schedule/2/paragraph/12 (the official version)
Page: https://openlegislation.uk/south-hook-combined-heat-and-power-plant-order-2014/schedule-2/paragraph-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.