# The South Hook Combined Heat and Power Plant Order 2014, Paragraph 18: Accumulations and deposits

Extent: E+W+S

(1) No authorised development comprised in Work No. 10A shall commence until a written scheme for the management of any accumulations or deposits whose effects may be harmful or visible or otherwise noticeable from outside the Order limits has been submitted to and approved by the relevant planning authority.
(2) The approved scheme for the management of accumulations and deposits must be implemented before and maintained during the construction, operation and decommissioning of the authorised development.

---
Source: https://www.legislation.gov.uk/uksi/2014/2846/schedule/2/paragraph/18 (the official version)
Page: https://openlegislation.uk/south-hook-combined-heat-and-power-plant-order-2014/schedule-2/paragraph-18
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.