{
  "url": "https://openlegislation.uk/south-hook-combined-heat-and-power-plant-order-2014/schedule-2/paragraph-7",
  "json_url": "https://openlegislation.uk/south-hook-combined-heat-and-power-plant-order-2014/schedule-2/paragraph-7.json",
  "legislation": "uksi/2014/2846",
  "legislation_title": "The South Hook Combined Heat and Power Plant Order 2014",
  "legislation_url": "https://openlegislation.uk/south-hook-combined-heat-and-power-plant-order-2014",
  "path": "schedule/2/paragraph/7",
  "kind": "paragraph",
  "number": "7",
  "heading": "Fencing and other means of enclosure",
  "text": "(1) All proposed permanent fences, walls or other means of enclosure must be constructed as identified in the written details referred to in requirement 5 (detailed design approval) unless otherwise agreed in writing by the relevant planning authorities prior to the completion of commissioning.\n(2) All construction areas must remain securely fenced at all times during construction of the authorised development.\n(3) Any fencing or means of enclosure not covered by paragraph (1) must be removed from the site within 6 months of the completion of commissioning.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 2 para. 7 in force at 23.10.2014, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2014/2846/schedule/2/paragraph/7",
    "retrieved_at": "2026-10-28T23:58:38.315870+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}