  "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021",
  "json_url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021.json",
  "id": "uksi/2021/1259",
  "title": "The South Humber Bank Energy Centre Order 2021",
  "short_title": "South Humber Bank Energy Centre 2021",
  "long_title": "This Order authorises EP Waste Management Limited (referred to in this Order as the undertaker) to construct, operate and maintain an energy from waste electricity generating station located on land at the South Humber Bank Power Station Site, South Marsh Road, near Stallingborough, Lincolnshire, fuelled by refuse derived fuels, with a capacity to process 753,500 tonnes of refuse derived fuel per annum, with a gross generation capacity of up to 95 megawatts at ISO conditions.",
  "citation": "S.I. 2021/1259",
  "type": "uksi",
  "year": "2021",
  "number": "1259",
  "version": "current",
  "date": "2021-11-10",
  "revised": true,
  "valid_from": "2022-04-05",
  "extent": "E+W+S",
  "unapplied_effects": 0,
  "provisions": [
    {
      "path": "introduction",
      "kind": "introduction",
      "number": null,
      "heading": "Introductory text",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/introduction",
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "part/1",
      "kind": "part",
      "number": "1",
      "heading": "PRELIMINARY",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "article/1",
      "kind": "article",
      "number": "1",
      "heading": "Citation and commencement",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-1",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/1"
    },
    {
      "path": "article/2",
      "kind": "article",
      "number": "2",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-2",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/1"
    },
    {
      "path": "article/3",
      "kind": "article",
      "number": "3",
      "heading": "Electronic Communications",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-3",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/1"
    },
    {
      "path": "part/2",
      "kind": "part",
      "number": "2",
      "heading": "PRINCIPAL POWERS",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "article/4",
      "kind": "article",
      "number": "4",
      "heading": "Development consent etc. granted by the Order",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-4",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2"
    },
    {
      "path": "article/5",
      "kind": "article",
      "number": "5",
      "heading": "Effect of the Order on the SHBEC planning permission",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-5",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2"
    },
    {
      "path": "article/6",
      "kind": "article",
      "number": "6",
      "heading": "Maintenance of authorised development",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-6",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2"
    },
    {
      "path": "article/7",
      "kind": "article",
      "number": "7",
      "heading": "Operation of authorised development",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-7",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2"
    },
    {
      "path": "article/8",
      "kind": "article",
      "number": "8",
      "heading": "Benefit of the Order",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-8",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2"
    },
    {
      "path": "article/9",
      "kind": "article",
      "number": "9",
      "heading": "Consent to transfer benefit of the Order",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-9",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2"
    },
    {
      "path": "part/3",
      "kind": "part",
      "number": "3",
      "heading": "STREETS",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "article/10",
      "kind": "article",
      "number": "10",
      "heading": "Street works",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-10",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3"
    },
    {
      "path": "article/11",
      "kind": "article",
      "number": "11",
      "heading": "Power to alter layout, etc., of streets",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-11",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3"
    },
    {
      "path": "article/12",
      "kind": "article",
      "number": "12",
      "heading": "Construction and maintenance of new or altered means of access",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-12",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3"
    },
    {
      "path": "article/13",
      "kind": "article",
      "number": "13",
      "heading": "Temporary stopping up of streets and public rights of way",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-13",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3"
    },
    {
      "path": "article/14",
      "kind": "article",
      "number": "14",
      "heading": "Agreements with street authorities",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-14",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3"
    },
    {
      "path": "part/4",
      "kind": "part",
      "number": "4",
      "heading": "SUPPLEMENTAL POWERS",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "article/15",
      "kind": "article",
      "number": "15",
      "heading": "Discharge of water",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-15",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/4"
    },
    {
      "path": "article/16",
      "kind": "article",
      "number": "16",
      "heading": "Authority to survey and investigate the land",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-16",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/4"
    },
    {
      "path": "part/5",
      "kind": "part",
      "number": "5",
      "heading": "OPERATIONS",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "article/17",
      "kind": "article",
      "number": "17",
      "heading": "Felling or lopping of trees",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-17",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/5"
    },
    {
      "path": "part/6",
      "kind": "part",
      "number": "6",
      "heading": "MISCELLANEOUS AND GENERAL",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "article/18",
      "kind": "article",
      "number": "18",
      "heading": "Protective provisions",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-18",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/6"
    },
    {
      "path": "article/19",
      "kind": "article",
      "number": "19",
      "heading": "Statutory undertakers",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-19",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/6"
    },
    {
      "path": "article/20",
      "kind": "article",
      "number": "20",
      "heading": "Apparatus and rights of statutory undertakers in stopped up streets",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-20",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/6"
    },
    {
      "path": "article/21",
      "kind": "article",
      "number": "21",
      "heading": "Recovery of costs of new connections",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-21",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/6"
    },
    {
      "path": "article/22",
      "kind": "article",
      "number": "22",
      "heading": "Application of landlord and tenant law",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-22",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/6"
    },
    {
      "path": "article/23",
      "kind": "article",
      "number": "23",
      "heading": "Operational land for purposes of the 1990 Act",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-23",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/6"
    },
    {
      "path": "article/24",
      "kind": "article",
      "number": "24",
      "heading": "Defence to proceedings in respect of statutory nuisance",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-24",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/6"
    },
    {
      "path": "article/25",
      "kind": "article",
      "number": "25",
      "heading": "Certification of plans, etc.",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-25",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/6"
    },
    {
      "path": "article/26",
      "kind": "article",
      "number": "26",
      "heading": "Service of notices",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-26",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/6"
    },
    {
      "path": "article/27",
      "kind": "article",
      "number": "27",
      "heading": "Procedure in relation to certain approvals, etc.",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-27",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/6"
    },
    {
      "path": "article/28",
      "kind": "article",
      "number": "28",
      "heading": "Requirements, appeals etc.",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-28",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/6"
    },
    {
      "path": "article/29",
      "kind": "article",
      "number": "29",
      "heading": "Arbitration",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/article-29",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/6"
    },
    {
      "path": "signature",
      "kind": "signature",
      "number": null,
      "heading": "Signature",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/signature",
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/1",
      "kind": "schedule",
      "number": "1",
      "heading": "AUTHORISED DEVELOPMENT",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-1",
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/2",
      "kind": "schedule",
      "number": "2",
      "heading": "REQUIREMENTS",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/2/paragraph/1",
      "kind": "paragraph",
      "number": "1",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-1",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/2",
      "kind": "paragraph",
      "number": "2",
      "heading": "Commencement of the authorised development and notices",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-2",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/3",
      "kind": "paragraph",
      "number": "3",
      "heading": "Approved details and amendments to them",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-3",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/4",
      "kind": "paragraph",
      "number": "4",
      "heading": "Requirement for written approval",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-4",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/5",
      "kind": "paragraph",
      "number": "5",
      "heading": "Detailed design (position and scale)",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-5",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/6",
      "kind": "paragraph",
      "number": "6",
      "heading": "Detailed design (appearance)",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-6",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/7",
      "kind": "paragraph",
      "number": "7",
      "heading": "Retained trees",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-7",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/8",
      "kind": "paragraph",
      "number": "8",
      "heading": "Means of enclosure and hard landscaping",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-8",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/9",
      "kind": "paragraph",
      "number": "9",
      "heading": "Lighting scheme",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-9",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/10",
      "kind": "paragraph",
      "number": "10",
      "heading": "Soft landscaping",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-10",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/11",
      "kind": "paragraph",
      "number": "11",
      "heading": "Biodiversity protection",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-11",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/12",
      "kind": "paragraph",
      "number": "12",
      "heading": "Biodiversity mitigation and enhancement",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-12",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/13",
      "kind": "paragraph",
      "number": "13",
      "heading": "Surface water drainage",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-13",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/14",
      "kind": "paragraph",
      "number": "14",
      "heading": "Foul water drainage",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-14",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/15",
      "kind": "paragraph",
      "number": "15",
      "heading": "Construction environmental management plan",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-15",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/16",
      "kind": "paragraph",
      "number": "16",
      "heading": "Construction traffic management and travel planning",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-16",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/17",
      "kind": "paragraph",
      "number": "17",
      "heading": "Piling",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-17",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/18",
      "kind": "paragraph",
      "number": "18",
      "heading": "Temporary halting of development on finding unexpected contamination",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-18",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/19",
      "kind": "paragraph",
      "number": "19",
      "heading": "Investigation and remediation of contamination",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-19",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/20",
      "kind": "paragraph",
      "number": "20",
      "heading": "Implementation of remediation scheme",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-20",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/21",
      "kind": "paragraph",
      "number": "21",
      "heading": "Procedure in cases of unexpected contamination",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-21",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/22",
      "kind": "paragraph",
      "number": "22",
      "heading": "Flood risk mitigation",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-22",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/23",
      "kind": "paragraph",
      "number": "23",
      "heading": "Flood warning and evacuation plan",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-23",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/24",
      "kind": "paragraph",
      "number": "24",
      "heading": "Delivery and servicing plan",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-24",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/25",
      "kind": "paragraph",
      "number": "25",
      "heading": "Operational travel plan",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-25",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/26",
      "kind": "paragraph",
      "number": "26",
      "heading": "Visibility splays",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-26",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/27",
      "kind": "paragraph",
      "number": "27",
      "heading": "New highway access",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-27",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/28",
      "kind": "paragraph",
      "number": "28",
      "heading": "Parking",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-28",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/29",
      "kind": "paragraph",
      "number": "29",
      "heading": "Road condition survey",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-29",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/30",
      "kind": "paragraph",
      "number": "30",
      "heading": "Air safety",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-30",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/31",
      "kind": "paragraph",
      "number": "31",
      "heading": "Fuel type",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-31",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/32",
      "kind": "paragraph",
      "number": "32",
      "heading": "Fuel storage",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-32",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/33",
      "kind": "paragraph",
      "number": "33",
      "heading": "Decommissioning",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-33",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/34",
      "kind": "paragraph",
      "number": "34",
      "heading": "Amendments agreed by the relevant planning authority",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-34",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/35",
      "kind": "paragraph",
      "number": "35",
      "heading": "Combined heat and power",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-35",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/36",
      "kind": "paragraph",
      "number": "36",
      "heading": "Anticipatory steps towards compliance with any requirement",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-36",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/37",
      "kind": "paragraph",
      "number": "37",
      "heading": "Heavy goods vehicle prohibition",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-37",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/38",
      "kind": "paragraph",
      "number": "38",
      "heading": "Development consent obligation",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-2/paragraph-38",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/3",
      "kind": "schedule",
      "number": "3",
      "heading": "DEEMED APPROVAL OF MATTERS REFERRED TO IN REQUIREMENTS",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-3",
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/4",
      "kind": "schedule",
      "number": "4",
      "heading": "STREETS SUBJECT TO STREET WORKS",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-4",
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/5",
      "kind": "schedule",
      "number": "5",
      "heading": "STREETS SUBJECT TO PERMANENT ALTERATION OF LAYOUT",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-5",
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/6",
      "kind": "schedule",
      "number": "6",
      "heading": "ACCESS",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/6/part/1",
      "kind": "part",
      "number": "1",
      "heading": "THOSE PARTS OF THE ACCESS TO BE MAINTAINED AT THE PUBLIC EXPENSE",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-6/part-1",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/6"
    },
    {
      "path": "schedule/6/part/2",
      "kind": "part",
      "number": "2",
      "heading": "THOSE PARTS OF THE ACCESS TO BE MAINTAINED BY THE STREET AUTHORITY",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-6/part-2",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/6"
    },
    {
      "path": "schedule/7",
      "kind": "schedule",
      "number": "7",
      "heading": "STREETS TO BE TEMPORARILY STOPPED UP",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-7",
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/8",
      "kind": "schedule",
      "number": "8",
      "heading": "PROTECTIVE PROVISIONS",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/8/part/1",
      "kind": "part",
      "number": "1",
      "heading": "FOR THE PROTECTION OF ANGLIAN WATER",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8"
    },
    {
      "path": "schedule/8/paragraph/1",
      "kind": "paragraph",
      "number": "1",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-1",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/1"
    },
    {
      "path": "schedule/8/paragraph/2",
      "kind": "paragraph",
      "number": "2",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-2",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/1"
    },
    {
      "path": "schedule/8/paragraph/3",
      "kind": "paragraph",
      "number": "3",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-3",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/1"
    },
    {
      "path": "schedule/8/paragraph/4",
      "kind": "paragraph",
      "number": "4",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-4",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/1"
    },
    {
      "path": "schedule/8/paragraph/5",
      "kind": "paragraph",
      "number": "5",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-5",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/1"
    },
    {
      "path": "schedule/8/paragraph/6",
      "kind": "paragraph",
      "number": "6",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-6",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/1"
    },
    {
      "path": "schedule/8/paragraph/7",
      "kind": "paragraph",
      "number": "7",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-7",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/1"
    },
    {
      "path": "schedule/8/paragraph/8",
      "kind": "paragraph",
      "number": "8",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-8",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/1"
    },
    {
      "path": "schedule/8/paragraph/9",
      "kind": "paragraph",
      "number": "9",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-9",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/1"
    },
    {
      "path": "schedule/8/part/2",
      "kind": "part",
      "number": "2",
      "heading": "FOR THE PROTECTION OF NATIONAL GRID AS ELECTRICITY AND GAS UNDERTAKER",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8"
    },
    {
      "path": "schedule/8/paragraph/10",
      "kind": "paragraph",
      "number": "10",
      "heading": "Application",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-10",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/2"
    },
    {
      "path": "schedule/8/paragraph/11",
      "kind": "paragraph",
      "number": "11",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-11",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/2"
    },
    {
      "path": "schedule/8/paragraph/12",
      "kind": "paragraph",
      "number": "12",
      "heading": "Apparatus of Undertakers in stopped up streets",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-12",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/2"
    },
    {
      "path": "schedule/8/paragraph/13",
      "kind": "paragraph",
      "number": "13",
      "heading": "Acquisition of apparatus",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-13",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/2"
    },
    {
      "path": "schedule/8/paragraph/14",
      "kind": "paragraph",
      "number": "14",
      "heading": "Removal of apparatus",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-14",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/2"
    },
    {
      "path": "schedule/8/paragraph/15",
      "kind": "paragraph",
      "number": "15",
      "heading": "Facilities and rights for alternative apparatus",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-15",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/2"
    },
    {
      "path": "schedule/8/paragraph/16",
      "kind": "paragraph",
      "number": "16",
      "heading": "Retained apparatus: protection Gas Undertakers",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-16",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/2"
    },
    {
      "path": "schedule/8/paragraph/17",
      "kind": "paragraph",
      "number": "17",
      "heading": "Retained apparatus: Protection: Electricity Undertakers",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-17",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/2"
    },
    {
      "path": "schedule/8/paragraph/18",
      "kind": "paragraph",
      "number": "18",
      "heading": "Expenses",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-18",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/2"
    },
    {
      "path": "schedule/8/paragraph/19",
      "kind": "paragraph",
      "number": "19",
      "heading": "Indemnity",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-19",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/2"
    },
    {
      "path": "schedule/8/paragraph/20",
      "kind": "paragraph",
      "number": "20",
      "heading": "Enactments and agreements",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-20",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/2"
    },
    {
      "path": "schedule/8/paragraph/21",
      "kind": "paragraph",
      "number": "21",
      "heading": "Co-operation",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-21",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/2"
    },
    {
      "path": "schedule/8/paragraph/22",
      "kind": "paragraph",
      "number": "22",
      "heading": "Access",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-22",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/2"
    },
    {
      "path": "schedule/8/paragraph/23",
      "kind": "paragraph",
      "number": "23",
      "heading": "Arbitration",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-23",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/2"
    },
    {
      "path": "schedule/8/paragraph/24",
      "kind": "paragraph",
      "number": "24",
      "heading": "Notices",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-24",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/2"
    },
    {
      "path": "schedule/8/part/3",
      "kind": "part",
      "number": "3",
      "heading": "FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8"
    },
    {
      "path": "schedule/8/paragraph/25",
      "kind": "paragraph",
      "number": "25",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-25",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/3"
    },
    {
      "path": "schedule/8/paragraph/26",
      "kind": "paragraph",
      "number": "26",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-26",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/3"
    },
    {
      "path": "schedule/8/paragraph/27",
      "kind": "paragraph",
      "number": "27",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-27",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/3"
    },
    {
      "path": "schedule/8/paragraph/28",
      "kind": "paragraph",
      "number": "28",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-28",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/3"
    },
    {
      "path": "schedule/8/paragraph/29",
      "kind": "paragraph",
      "number": "29",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-29",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/3"
    },
    {
      "path": "schedule/8/paragraph/30",
      "kind": "paragraph",
      "number": "30",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-30",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/3"
    },
    {
      "path": "schedule/8/paragraph/31",
      "kind": "paragraph",
      "number": "31",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-31",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/3"
    },
    {
      "path": "schedule/8/paragraph/32",
      "kind": "paragraph",
      "number": "32",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-32",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/3"
    },
    {
      "path": "schedule/8/paragraph/33",
      "kind": "paragraph",
      "number": "33",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-33",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/3"
    },
    {
      "path": "schedule/8/paragraph/34",
      "kind": "paragraph",
      "number": "34",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-34",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/3"
    },
    {
      "path": "schedule/8/paragraph/35",
      "kind": "paragraph",
      "number": "35",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-35",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/3"
    },
    {
      "path": "schedule/8/part/4",
      "kind": "part",
      "number": "4",
      "heading": "FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8"
    },
    {
      "path": "schedule/8/paragraph/36",
      "kind": "paragraph",
      "number": "36",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-36",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/4"
    },
    {
      "path": "schedule/8/paragraph/37",
      "kind": "paragraph",
      "number": "37",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-37",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/4"
    },
    {
      "path": "schedule/8/paragraph/38",
      "kind": "paragraph",
      "number": "38",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-38",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/4"
    },
    {
      "path": "schedule/8/paragraph/39",
      "kind": "paragraph",
      "number": "39",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-39",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/4"
    },
    {
      "path": "schedule/8/paragraph/40",
      "kind": "paragraph",
      "number": "40",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-40",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/4"
    },
    {
      "path": "schedule/8/part/5",
      "kind": "part",
      "number": "5",
      "heading": "FOR THE PROTECTION OF NETWORK RAIL",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8"
    },
    {
      "path": "schedule/8/paragraph/41",
      "kind": "paragraph",
      "number": "41",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-41",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/5"
    },
    {
      "path": "schedule/8/paragraph/42",
      "kind": "paragraph",
      "number": "42",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-42",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/5"
    },
    {
      "path": "schedule/8/paragraph/43",
      "kind": "paragraph",
      "number": "43",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-43",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/5"
    },
    {
      "path": "schedule/8/paragraph/44",
      "kind": "paragraph",
      "number": "44",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-44",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/5"
    },
    {
      "path": "schedule/8/paragraph/45",
      "kind": "paragraph",
      "number": "45",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-45",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/5"
    },
    {
      "path": "schedule/8/paragraph/46",
      "kind": "paragraph",
      "number": "46",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-46",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/5"
    },
    {
      "path": "schedule/8/paragraph/47",
      "kind": "paragraph",
      "number": "47",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-47",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/5"
    },
    {
      "path": "schedule/8/paragraph/48",
      "kind": "paragraph",
      "number": "48",
      "heading": null,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/schedule-8/paragraph-48",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8/part/5"
    },
    {
      "path": "note",
      "kind": "note",
      "number": null,
      "heading": "Explanatory note",
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/note",
      "extent": "E+W+S",
      "status": null,
      "parent": null
    }
  ],
  "has_text": true,
  "pdfs": [
    {
      "title": "Printed copy",
      "main": true,
      "language": null,
      "date": "2021-11-15",
      "size": 344893,
      "url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/pdf/uksi_20211259_en.pdf",
      "source_url": "https://www.legislation.gov.uk/uksi/2021/1259/pdfs/uksi_20211259_en.pdf"
    }
  ],
  "outstanding_effects": [],
  "made_under": [
    {
      "id": "ukpga/2008/29",
      "title": "Planning Act 2008",
      "url": "https://openlegislation.uk/planning-act-2008",
      "provisions": []
    }
  ],
  "changes_made_to": 129,
  "changes_made_to_url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/changes.json",
  "changes_made_by": 131,
  "changes_made_by_url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/changes/by-it.json",
  "instruments_made_under": 0,
  "instruments_made_under_url": "https://openlegislation.uk/south-humber-bank-energy-centre-order-2021/instruments.json",
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2021/1259",
    "retrieved_at": "2026-10-28T22:07:14.978746+00:00"
  },
  "licence": "Open Government Licence v3.0",