# The Southampton to London Pipeline Development Consent Order 2020, Paragraph 1: Interpretation


In this Part—
“archaeological mitigation strategy” means the strategy of that description set out in Schedule 11 (documents to be certified) and certified as the archaeological mitigation strategy by the Secretary of State for the purposes of this Order;
“CEP” means the community engagement plan to be prepared and approved under Requirement 15 (community engagement plan);
“contamination” means contamination of any land (including groundwater) within the Order limits which has not been previously identified in the environmental statement which is in the reasonable opinion of the undertaker likely to affect the construction of the authorised development and/or cause significant harm to persons or pollution of controlled waters or the environment;
“CTMP” means the construction traffic management plan to be prepared and approved under Requirement 7 (construction traffic management plan);
“European protected species” has the same meaning as in regulations 42 (European protected species of animals) and 46 (European protected species of plants) of the Conservation of Habitats and Species Regulations 2017;
“existing fuel pipeline” means so much of the existing Jetline pipeline from the undertaker’s Fawley refinery in Hampshire to the undertaker’s West London Terminal storage facility in the London Borough of Hounslow as is to be replaced by the pipeline works;
“Habitats Regulations Assessment” means the document of that description set out in Schedule 11 (documents to be certified) and certified as the Habitats Regulations Assessment by the Secretary of State for the purposes of this Order;
“HRA Commitments Schedule” means the document of that description set out in Schedule 11 (documents to be certified) and certified as the HRA Commitments Schedule by the Secretary of State for the purposes of this Order;
“indicative layout drawings” means the drawings of that description set out in Schedule 11 (documents to be certified) and certified as the indicative layout drawings by the Secretary of State for the purposes of this Order;
“Lead Local Flood Authority” means Hampshire County Council or Surrey County Council, as the case may be;
“LEMP” means the landscape and ecological management plan to be prepared and approved under Requirement 12 (landscape and ecological management plan);
“nationally protected species” means any species protected under the Wildlife and Countryside Act 1981;
“outline CEP” means the document of that description set out in Schedule 11 (documents to be certified) and certified as the outline CEP by the Secretary of State for the purposes of this Order;
“outline CEMP” means the document of that description set out in Schedule 11 (documents to be certified) and certified as the outline CEMP by the Secretary of State for the purposes of this Order;
“outline CTMP” means the document of that description set out in Schedule 11 (documents to be certified) and certified as the outline CTMP by the Secretary of State for the purposes of this Order;
“outline LEMP” means the document of that description set out in Schedule 11 (documents to be certified) and certified as the outline LEMP by the Secretary of State for the purposes of this Order;
“outline SFWDP” means the document of that description set out in Schedule 11 (documents to be certified) and certified as the outline SFWDP by the Secretary of State for the purposes of this Order;
“protected species” means European protected species or nationally protected species;
“relevant authority” means the body responsible for giving a consent, agreement or approval under this Schedule;
“SDNP Schedule” means the document of that description set out in Schedule 11 (documents to be certified) and certified as the SDNP Schedule by the Secretary of State for the purposes of this Order;
“Site Specific Plans” means the plans of that description set out in Schedule 11 (documents to be certified) and certified as the site specific plans by the Secretary of State for the purposes of this Order;
“SSSI working plans” means the plans of that description showing the method of working in sites of special scientific interest as set out in Appendix B of the Habitats Regulations Assessment; and
“stage” means a defined spatial section or part of the authorised development, the extent of which is shown in a scheme submitted to the relevant planning authority pursuant to Requirement 3 (stages of authorised development).

---
Source: https://www.legislation.gov.uk/uksi/2020/1099/schedule/2/paragraph/1 (the official version)
Page: https://openlegislation.uk/southampton-to-london-pipeline-development-consent-order-2020/schedule-2/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.