Paragraph 12 Landscape and ecological management plan
(1)
Subject to sub-paragraph (3), no stage of the authorised development must commence until a LEMP, for that stage, in accordance with the outline LEMP and the SSSI working plans, has been submitted to and approved by the relevant planning authority.
(2)
The LEMP must include an implementation timetable and must be carried out as approved.
(3)
Sub-paragraph (1) only applies to those stages of the authorised development in respect of which any landscape and ecological management measures are to be implemented by the undertaker, as identified in the outline LEMP.
(4)
The LEMP submitted for approval under sub-paragraph (1) must include the mitigation measures to be secured by the LEMP as set out in the HRA Commitments Schedule.