# The Southampton to London Pipeline Development Consent Order 2020, Paragraph 15: Community engagement plan


(1) No stage of the authorised development must commence until a CEP for that stage, in accordance with the outline CEP, has been submitted to and approved by the relevant planning authority.
(2) The CEP for each stage must be implemented as approved.

---
Source: https://www.legislation.gov.uk/uksi/2020/1099/schedule/2/paragraph/15 (the official version)
Page: https://openlegislation.uk/southampton-to-london-pipeline-development-consent-order-2020/schedule-2/paragraph-15
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.