OpenLegislation

Paragraph 18 Removal of above-ground infrastructure

Original text. Later amendments are not shown.

(1)

The undertaker must as soon as reasonably practicable following the abandonment of the authorised development, and in any event within six months of that date, remove any above-ground infrastructure, including for the avoidance of doubt, any aerial markers, cathodic protection test posts, cathodic protection rectifier cabinets and field boundary markers, to ground level.

(2)

In this Requirement—

(a)

“abandonment” means a final determination by the undertaker to permanently cease operating the authorised development; and

(b)

“above-ground infrastructure” means any part of the authorised development located above the surface of the ground which is not required for the operation of any other infrastructure owned or operated by the undertaker.