(1) Where an application has been made to a relevant authority for any consent, agreement or approval under a Requirement, the relevant authority must give notice to the undertaker of its decision on the application within a period of 42 days beginning with—
(a) where no further information is requested under Requirement 25, the day immediately following that on which the application is received by the authority;
(b) where further information is requested under Requirement 25, the day immediately following that on which further information has been supplied by the undertaker; or
(c) such longer period as may be agreed in writing by the undertaker and the relevant authority.
(2) In the event that the relevant authority does not determine an application within the period set out in sub-paragraph (1), the relevant authority is taken to have granted all parts of the application (without any condition or qualification) at the end of that period unless otherwise agreed in writing.

---
Source: https://www.legislation.gov.uk/uksi/2020/1099/schedule/2/paragraph/23 (the official version)
Page: https://openlegislation.uk/southampton-to-london-pipeline-development-consent-order-2020/schedule-2/paragraph-23
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.