# The Southampton to London Pipeline Development Consent Order 2020, Paragraph 7: Construction traffic


(1) Save in respect of matters approved in accordance with article 13 (temporary closure, alteration, diversion or restriction of streets and public rights of way) no stage of the authorised development must commence until a CTMP for that stage, in accordance with the outline CTMP, has been submitted to and approved by the relevant planning authority following consultation with the relevant highway authority.
(2) The CTMP for each stage must be implemented as approved.

---
Source: https://www.legislation.gov.uk/uksi/2020/1099/schedule/2/paragraph/7 (the official version)
Page: https://openlegislation.uk/southampton-to-london-pipeline-development-consent-order-2020/schedule-2/paragraph-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.