# The Southampton to London Pipeline Development Consent Order 2020, Paragraph 118


Save for differences or disputes arising under paragraphs 112 and 114(5) any difference or dispute arising between the undertaker and SGN under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and SGN, be determined by arbitration in accordance with article 48 (arbitration).

---
Source: https://www.legislation.gov.uk/uksi/2020/1099/schedule/9/paragraph/118 (the official version)