# The Southampton to London Pipeline Development Consent Order 2020, Paragraph 24


The undertaker must—
(a) at all times afford reasonable facilities to the engineer for access to a specified work during its construction; and
(b) supply the engineer with all such information as the engineer may reasonably require with regard to a specified work or the method of constructing it.

---
Source: https://www.legislation.gov.uk/uksi/2020/1099/schedule/9/paragraph/24 (the official version)
Page: https://openlegislation.uk/southampton-to-london-pipeline-development-consent-order-2020/schedule-9/paragraph-24
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

