# Space Industry Act 2018, Paragraph 2


(1) Before making an application for an order under section 39 or for a land order, the licensee must—
(a) publish a notice in one or more newspapers circulating in the locality in which the land is situated;
(b) serve a notice on every owner, lessee and occupier of any of the land;
(c) serve a notice on every local authority within whose area any of the land is situated.
(2) A notice published or served under sub-paragraph (1) must—
(a) state that the licensee proposes to apply for an order;
(b) state the effect of the order that is to be applied for;
(c) specify the day by which, and the manner in which, any objections to the proposed order may be made.
(3) The day specified under sub-paragraph (2)(c) must not fall before the end of the period of 42 days beginning with the day on which the notice is published or served.

---
Source: https://www.legislation.gov.uk/ukpga/2018/5/schedule/6/paragraph/2 (the official version)
Page: https://openlegislation.uk/space-industry-act-2018/schedule-6/paragraph-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.