  "url": "https://openlegislation.uk/springwell-solar-farm-order-2026/schedule-15/paragraph-71",
  "json_url": "https://openlegislation.uk/springwell-solar-farm-order-2026/schedule-15/paragraph-71.json",
  "legislation": "uksi/2026/419",
  "legislation_title": "The Springwell Solar Farm Order 2026",
  "legislation_url": "https://openlegislation.uk/springwell-solar-farm-order-2026",
  "path": "schedule/15/paragraph/71",
  "kind": "paragraph",
  "number": "71",
  "heading": null,
  "text": "(1) Before beginning to construct any grid connection works, or any part of it, the undertaker must submit to NGET plans of the relevant grid connection works (or part of it) and such further particulars available to it as NGET may request within 21 days of receipt of the plans reasonably requested.\n(2) Any grid connection works must not be constructed except in accordance with such plans as may be approved in writing by NGET.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 15 para. 71 in force at 30.4.2026, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2026/419/schedule/15/paragraph/71",
    "retrieved_at": "2026-10-28T21:02:38.918571+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}