# The Springwell Solar Farm Order 2026, Paragraph 1

Extent: E+W

In this Schedule—
“relevant planning authority” means North Kesteven District Council, except for the following requirements where it shall mean Lincolnshire County Council—
(i) Requirement 7 (battery safety management);
(ii) Requirement 10 (drainage);
(iii) Requirement 11 (archaeology);
(iv) Requirement 14 (construction traffic management plan); and
(v) Requirement 17 (public right of way and permissive path management plan).

---
Source: https://www.legislation.gov.uk/uksi/2026/419/schedule/2/paragraph/1 (the official version)
Page: https://openlegislation.uk/springwell-solar-farm-order-2026/schedule-2/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

