# The Springwell Solar Farm Order 2026, Paragraph 1

Extent: E+W

In this Schedule—
“relevant planning authority” means North Kesteven District Council, except for the following requirements where it shall mean Lincolnshire County Council—
Requirement 7 (battery safety management);
Requirement 10 (drainage);
Requirement 11 (archaeology);
Requirement 14 (construction traffic management plan); and
Requirement 17 (public right of way and permissive path management plan).

---