# The Steeple Renewables Project Order 2026, Article 32: Compulsory acquisition of land – incorporation of the mineral code


Parts 2 and 3 of Schedule 2 (minerals) to the Acquisition of Land Act 1981 are incorporated into this Order subject to the modifications that—
(a) for “the acquiring authority” substitute “the undertaker”;
(b) for the “undertaking” substitute “authorised development”; and
(c) paragraph 8(3) is not incorporated.

---
Source: https://www.legislation.gov.uk/uksi/2026/1086/article/32 (the official version)
Page: https://openlegislation.uk/steeple-renewables-project-order-2026/article-32
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.