(1)

West Burton must give the undertaker reasonable notice of not less than 3 months of any such claim or demand from the date of such claim or demand arising and no settlement or compromise shall be made, unless payment is required in connection with a statutory compensation scheme, without first consulting the undertaker and considering its representations.

(2)

West Burton must use its reasonable endeavours to mitigate in whole or in part and to minimise any costs, expenses, loss, demands, and penalties to which the indemnity under this paragraph applies. If requested to do so by the undertaker, West Burton must provide an explanation of how the claim has been minimised. The undertaker is only liable under this paragraph for claims reasonably incurred by West Burton.

(3)

The fact that any work or thing has been executed or done with the consent of West Burton and in accordance with any conditions or restrictions prescribed by West Burton or in accordance with any plans approved by West Burton or to its satisfaction or in accordance with any directions or award of any arbitrator does not relieve the undertaker from any liability under this Part.