  "heading": "Expenses",
  "text": "Save where otherwise agreed in writing between UKAEA and the undertaker and subject to the following provisions of this paragraph, the undertaker must pay to UKAEA within 30 days of receipt of an itemised invoice or claim from UKAEA all charges, costs and expenses reasonably and properly incurred by UKAEA in consequence of the execution of the specified works including without limitation—\n(a) the approval of plans;\n(b) the carrying out of protective works, plus a capitalised sum to cover the cost of maintaining and renewing permanent protective works where such responsibilities fall to UKAEA; or\n(c) the survey of any land, apparatus or works, the inspection and monitoring of works or the installation or removal of any temporary works reasonably necessary in consequence of the execution of any such works referred to in this Part of this Schedule.",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2026/1086/schedule/10/paragraph/154",
    "retrieved_at": "2026-10-31T10:33:45.735898+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}