# The Steeple Renewables Project Order 2026, Paragraph 174: Access


If in consequence of the agreement reached in accordance with paragraph 166(1) or the powers granted under this Order the access to any apparatus is materially obstructed, the undertaker must provide such alternative means of access to such apparatus as will enable National Grid Electricity Transmission Plc to maintain or use the apparatus no less effectively than was possible before such obstruction.

---
Source: https://www.legislation.gov.uk/uksi/2026/1086/schedule/10/paragraph/174 (the official version)
Page: https://openlegislation.uk/steeple-renewables-project-order-2026/schedule-10/paragraph-174
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.