Paragraph 15 Public rights of way diversions

Original text. Later amendments are not shown.

(1)

No phase of the authorised development can commence and no decommissioning will be undertaken until a public rights of way management plan (as part of the outline CTMP) for any sections of public rights of way shown to be temporarily closed on the streets, access and rights of way plans for that phase has been submitted to and approved by the local planning authority in consultation with the relevant highway authority.

(2)

The plan must include details of—

(a)

measures to minimise the length of any sections of public rights of way to be temporarily closed;

(b)

advance publicity and signage in respect of any sections of public rights of way to be temporarily closed;

(c)

the locations of any public rights of way to be temporarily closed;

(d)

the hours of proposed works effecting public rights of way; and

(e)

measures to safeguard users of public rights of way during construction of the authorised development.

(3)

The plan must be implemented and thereafter maintained in accordance with the details approved under sub-paragraph (1).