# The Steeple Renewables Project Order 2026, Paragraph 17: Fencing and other means of enclosure


(1) No phase of the authorised development can commence until written details of all proposed permanent and temporary fences, walls or other means of enclosure of the connection works for that phase have been submitted to and approved by the local planning authority as part of the detailed design approval required by requirement 3(1) of this Schedule.
(2) No site preparation works can commence until written details of all proposed temporary fences, walls or other means of enclosure for the site preparation works have been submitted to and approved by the local planning authority.
(3) Any proposed temporary fences, walls or other means of enclosure for the site preparation works must be carried out in accordance with the approved details.
(4) Any construction site must remain securely fenced in accordance with the approved details at all times during construction of the authorised development.
(5) Any permanent fencing must be completed before the date of final commissioning of the authorised development in accordance with the written details established by sub-paragraph (1) and thereafter maintained in accordance with the approved details.
(6) Any temporary fencing must be removed on completion of the phase of construction of the authorised development for which it was used.
(7) For the purposes of this paragraph “commence” includes any site preparation works.

---
Source: https://www.legislation.gov.uk/uksi/2026/1086/schedule/2/paragraph/17 (the official version)
Page: https://openlegislation.uk/steeple-renewables-project-order-2026/schedule-2/paragraph-17
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.