# The Steeple Renewables Project Order 2026, Paragraph 2: Phases of authorised development and date of final commissioning


(1) The authorised development must not commence until a written scheme setting out the phases of construction of the authorised development has been submitted to and approved by the local planning authority.
(2) The scheme submitted pursuant to sub-paragraph (1) must include a timetable for the construction of the phases of the authorised development and a plan identifying the phasing areas.
(3) The scheme submitted and approved pursuant to sub-paragraph (1) must be implemented as approved.
(4) Notice of the date of final commissioning with respect of the first phase of Work No. 1 to complete commissioning must be given to the local planning authority within 15 working days of the date of final commissioning for that phase.

---
Source: https://www.legislation.gov.uk/uksi/2026/1086/schedule/2/paragraph/2 (the official version)
Page: https://openlegislation.uk/steeple-renewables-project-order-2026/schedule-2/paragraph-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.