  "text": "(1) The undertaker may, for the purposes of the authorised development—\n(a) form and lay out the permanent means of access, or improve existing means of access, in the locations specified in the table in Schedule 6 (access to works); and\n(b) with the approval of the local planning authority after consultation with the highway authority, form and lay out such other means of access or improve existing means of access, at such locations within the Order limits as the undertaker reasonably requires for the purposes of the authorised development.\n(2) If the local planning authority receives an application for approval under paragraph 14(1)(b) and fails to notify the undertaker of its decision within 56 days of receiving the application, that authority will be deemed to have granted approval.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Art. 14 in force at 13.11.2025, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/1175/article/14",
    "retrieved_at": "2026-10-28T21:09:52.508378+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}