# The Stonestreet Green Solar Order 2025, Paragraph 5: Work No. 5

Extent: E+W+S

Works including—
(a) fencing, gates, boundary treatment and other means of enclosure;
(b) provision of security and monitoring measures such as CCTV columns, lighting columns and lighting, a fence detection system, cameras, weather stations, and communication infrastructure;
(c) laying of electrical cables, including but not limited to electrical cables connecting Work No. 1, Work No. 2 and Work No. 3, including works to allow electrical cables crossings of non-navigable rivers, other watercourses and drains, permissive paths, public rights of way and other highways;
(d) works to allow installation of bridge crossings over non-navigable rivers and other watercourses and drains;
(e) laying down of internal access tracks (including fire access tracks), improvement of existing tracks, ramps, means of access, and roads, including construction signage and information boards;
(f) provision of water tanks and pipework connection to hydrants located at inverter stations where BESS installed; and
(g) equipment and materials storage during construction and decommissioning phases;

---
Source: https://www.legislation.gov.uk/uksi/2025/1175/schedule/1/paragraph/5 (the official version)
Page: https://openlegislation.uk/stonestreet-green-solar-order-2025/schedule-1/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.