# The Stonestreet Green Solar Order 2025, Paragraph 7: Work No. 7

Extent: E+W+S

Construction and decommissioning works including—
(a) compound areas including hardstanding, turning and loading areas, car parking, offices/welfare facilities, storage areas, waste skip areas, solar PV panel testing area, bunded area for storage of fuels and hydrocarbons, security fencing and hoarding; and
(b) an internal haulage road comprising temporary permeable ground protection mats including passing bays, means of access, and signage;

---
Source: https://www.legislation.gov.uk/uksi/2025/1175/schedule/1/paragraph/7 (the official version)
Page: https://openlegislation.uk/stonestreet-green-solar-order-2025/schedule-1/paragraph-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.