The undertaker must no later than 20 Business Days from the date that the documents referred to in article 41 (certification of plans, etc.) are submitted to and certified by the Secretary of State in accordance with article 41 (certification of plans, etc.), provide a set of those documents to the Company in a digital format reasonably specified by the Company.

---