# The Stonestreet Green Solar Order 2025, Paragraph 10: Public rights of way

Extent: E+W+S

(1) No phase of the authorised development incorporating any part of a public right of way which is to be temporarily closed or permanently stopped up pursuant to article 17 (public rights of way – stopping up and vehicular use on public rights of way) may commence until a RoWAS for the phase has been submitted to and approved by the local planning authority, such approval to be in consultation with Kent County Council.
(2) The RoWAS submitted pursuant to sub-paragraph (1) must—
(a) include details of measures to minimise the distance of any sections of the public right of way to be temporarily closed or permanently stopped up;
(b) include details of advance publicity and signage in respect of any sections of public rights of way to be temporarily closed or permanently stopped up; and
(c) be generally in accordance with the outline RoWAS.
(3) The RoWAS for each phase of the authorised development must be implemented as approved and maintained for that phase.

---
Source: https://www.legislation.gov.uk/uksi/2025/1175/schedule/2/paragraph/10 (the official version)